Tuesday, November 11, 2008

Red Trail Report - SIX COES by EOY??

SKUNK NEWSFLASH
Richardton, ND
Third Quarter Report - Newsletter

This update from the Red Trail Plant Manager; page one of the scheduled 8th COES 3Q Newsletter:

"In addition to regular plant operations, current projects include the installation of equipment and components for corn oil extraction. We plan to have this project completed by the end of 2008. We look forward to the additional revenue stream, as we will be selling corn oil for the production of biodiesel.

This update from the General Manager's comments on page two:

"Plan's for RTE's corn oil extraction project are well underway (scheduled completion in December 2008) and will add diversity to the plant's revenue stream."

Newsletter
http://redtrailenergyllc.com/images/uploads/Red_Trail_Report_-_Q3-2008_1.pdf

According to the 2Q, page 28 Richardton is scheduled for completion, 4Q 2008. After rereading the 11 October blog, the Skunk sees that Richardton ND was not mentioned. The SkunK wrongly figured it was mentioned here:

"1. COES#6 and COES#7 are delayed and are now scheduled for commissioning in Q1 2009. "

11 OCT Blog
http://greenshift-gers.blogspot.com/2008/10/message-from-greenshift-ceo.html

COES #6 & #7 mentioned here may instead refer to the delay of the two COES scheduled for Lakota. If this is true then we may be set for six COES by EOY rather than the five the SkunK had figured. That would be only one short of the seven the company sees as the turning point as to when they turn profitable.

SkunK